Responsible for planning and managing budgets for company projects, NIYARM Fashion-Ramintra, AKAD-Pratunam Phra IN and MONTE NIQUE (Rangsit)
• Responsible for project management, Budget control and work planning and coordinate relevant parties according to goals and plans.
• Create a Microsoft Project work plan, update project progress in real-time, and summarize reports for management.
• Review payment processing, process project claims, and control the issuance of purchase requisitions (PR) within the budget for hiring services.
• Control and update approved documentation, and notify all parties before ordering and using materials in construction.
• Verify details, specifications, compare prices of materials and equipment, and submit approval requests in a timely manner according plan and Collect and issue documents for additions and deletions of tasks.
• Summarize change reports including additional costs and construction timelines.
• Summarize actual expenses compared to the budget and estimate future costs until project completion, and seek approval for work methods, material usage, testing standards, and record-keeping.
• Prepare weekly and monthly project reports.
กรกฎาคม 2568 ถึง มิถุนายน 2567
Senior Office Engineer
เอ็นเอ็มซี คอนด์แลนด์ จำกัด
สำหรับสมาชิกเท่านั้น
Market Place Theprak Project by SIAM FUTURE DEVELOPMENT COMPANY from opening project to practical completion and final completion, and now work in Dusit Central Park Project.
• Control and supervise all project documents, Make S-Curve plans, Material approve plans and Shop Drawing approve plans and inspect materials according list of assemblies and submit them for approval.
• Prepare weekly report and present, weekly work plans, survey and check work progress for monthly payment and report monthly payment.
• Check and procure materials and contract in comparison with budget and control quantities according project budget.
• Gather all information and documents from initiation to final completion project.
สิงหาคม 2567 ถึง มิถุนายน 2566
PROJECT ENGINEER
PMC INTERCORE CO., LTD.
สำหรับสมาชิกเท่านั้น
SARANSIRI SALAYA-PINKLAO by SANSIRI, responsible for all facilities section’s Project.
• Construction control, prepare drawing for construction according work plan.
• Estimate amount of work, check price and compare price with budget and take memorandum for approved.
• Make a materials approved plan and Shop Drawing approve plan and prepare document for approved.
BURAPA CONCRETE and CONSTRUCTION CO., LTD.
ASSISTANAT PROJECT MANAGER | AUGUST 2022 to JULY 2023
Ministry of Dream, Pilin Cambodia, from opening project to final Structure phase.
• Control and supervise all project documents, Make S-Curve plans, Material approve plans and Shop Drawing approve plans and inspect materials according list of assemblies and submit them for approval.
• Manage contractors and investigate material prices to compare with budget and plan procurement to be consistent with project plans.
• Take cost control Plan for project and control project budget.
• Prepare shop drawing and clear before constructure.
Scope Co., Ltd. :
Senior Project Coordinator | FEBRUARY 2020 to AUGUST 2022
Scope Promsri from opening project to final and transfer and Scope Thonglor, pre- Construction to Constructure.
• Attend a meeting regarding the referendum About construction projects according to EIA measures.
• Host the preparation of TOR together with the hiring department for use in special hiring and/or tending (TENDER) to keep up with the specified hiring plan.
• Responsible for project management, Budget control and work planning and coordinate relevant parties according to goals and plans.
• Plan project budgets and cash flow for cash according to the fiscal year.
• Manage the work according to the plan Contractor and Consult Budget.
• Participate in price considerations negotiate price conditional quality check and within the budget and compare VO VE with budget.
• Review the draft contract procurement plan.
• Coordinate with other relevant departments within the organization and in its affiliates.
Tipakorn Co., Ltd
SENIOR OFFICE ENGINEER | NOVEMBER 2017 to FEBRUARY 2020
Track Doubling for East Coast Line Project (Chacheongsao-Khlong Sip Kao-Kaeng Khoi) by SRT, from opening project to final Struction.
• Prepare Drawing for Construction and As-Built Drawing.
• Check out the Workload to do BOQ and Master Schedule with Cash Flow.
• Make a material equipment approval plan and Shop Drawing Approval Plans
• Document for equipment approval and Shop Drawing approval for construction.
• Prepare documents for payment and Check the workload and set up the contractors portfolio.
NARA Consult and Design Co., Ltd. :
PROJECT ENGINEER | OCTOBER 2013 to NOVEMBER 2017
ARIA Asoke by AQ Estate (Chewathai Residence Asoke) from opening project to final and transfer AND LAVIQ Sukhumvit 57 by Real asset, pre-Construction to Final Structure phase.
• Participated in a public hearing meeting before starting construction according to EIA and considering construction measures according to EIA.
• Check Detail Contracts and Contract Documents.
• Attend the contractor hiring meeting.
• Master Schedule with Cash Flow
• Check out the Contractor's plans.
• Check the Contractor's Daily Attendance Record. (Daily Request , Daily Report)
• Prepare Weekly and Monthly Reports and Certificate Payment Contract.
• Review the Drawing for Check the Project Budget.
• Supervise and control bored pile work (Dry Process).
• Supervise the construction according to standards and project plans.
ประวัติการฝึกอบรม
ไม่ได้ระบุ
The Interpreter way Class 12 Road Association of Thailand
นายช่างคุมงานก่อสร้างทาง
ความสามารถ
ความสามารถทางภาษา
พูด (ดีมาก) อ่าน (ดีมาก) เขียน (ดีมาก)
พูด (ดี) อ่าน (ดี) เขียน (ดี)
ไทย 50 คำ/นาที อังกฤษ 65 คำ/นาที
รถยนต์ ,
รถยนต์ ,
Microsoft Office, MS.Project Power Point, Auto CAD, ERP, CITRIX, CONZOL, MANGO
โครงการ / ผลงาน / เกียรติประวัติ / บุคคลอ้างอิง
- Market Place Theprak Project by SIAM FUTURE DEVELOPMENT COMPANY
- Dusit Central Park
- SARANSIRI SALAYA-PINKLAO by SANSIRI
- Scope Promsri and Scope Thonglor
- Track Doubling for East Coast Line Project (Chacheongsao-Khlong Sip Kao-Kaeng Khoi) by SRT
- ARIA Asoke by AQ Estate (Chewathai Residence Asoke)